Outline Changes Tutorial
With Date | Without Date
- Select "Outline Changes only " in the outline report box.
|
|
- Press Submit. (Picture below is the report you should recieve. It
should show the outline and all outline changes since the outline
was made. )
|
- Select "Outline Changes only" in the outline report box.
Enter the first date you want changes to be shown for. (Date should
be in the form "010203" where "01" is the year,
"02" is the month, and "03" is the day)
|
|
- Press Submit. (Picture below is the report you should recieve. It
should show the outline and all outline changes since the date specified.
)
|
Tutorial Home
Home | Project Summary
| Weekly Journal |
VRV-ET | DMP | Visit
Journal | My Homepage
| Jan's Homepage | Final
Report